What Comes Next?

    As the Downtown Roadway Project moves forward, here’s what residents and businesses can expect in the coming weeks:

    • May 19: An approximate one-week closure at Canal Street for crosswalk upgrades and final water testing.

    • June 9 and beyond: Rolling closures across Main Street for striping and one-way traffic changes. These will affect small segments at a time, with flaggers guiding traffic.

    • Late June/July: Median work on 16th Street, requiring periodic lane closures.

    Throughout the remainder of the project, the City will continue to provide updates through:

    • Weekly social media videos with the project manager

    • City Council/Board of Supervisors public comments

    • Updated street signage and detour maps

    • News interviews and press updates

    We recognize the disruptions these changes may bring, but these improvements will result in a safer, better-connected downtown. Thank you for your continued patience and support.